GovernmentDepartments & Services
CommunityBusinessHow Do I?
Click to Home
Go To Search
Street Projects

18th Avenue South from Southview Boulevard to Marie Ave.

Due to a severe watermain break, the City will be reconstructing this street in 2017. On July 31st, Danner, Inc. was awarded the contract and tentatively plans to start construction by the end of August with a completion date at the end of October.  

18th Avenue South Repairs Fact Sheet


CONSTRUCTION UPDATE WEEK OF JULY 31, 2017:

Armour Avenue: Completed:  
Milling, curb& gutter, sidewalk and pedestrian ramps, remove and replace castings.
To do:
Detail milling, pave wear course, irrigation repairs, turf restoration, clean up

Bridgepoint Drive: Completed:
 Remove bituminous, Remove and Replace castings, Adjust gate valves, curb & gutter, Base course paved
To do: Pave wear course, turf restoration, clean up

Concord Exchange:
Completed:  Remove bituminous, Remove and Replace castings, adjust gate valves, curb & gutter, Base course paved
To do: Pave wear course, turf restoration, clean up

Grand Avenue:
Completed: Remove bituminous, Remove and Replace castings, Adjust gate valves, curb & gutter, sidewalk, Base course paved
To do: Pave wear course, turf restoration, clean up

5th Avenue No.: Completed:  sidewalk and pedestrian ramps
To do: Remove bituminous, remove and replace castings, adjust gate valves, pave base course, pave wear course, turf restoration, clean up

15th Avenue:
Completed:  Remove bituminous
To do: Remove and replace castings, grade gravel for paving, pave base course, pave wear course, clean up

16th Avenue:
Completed:  Remove bituminous
 To do: Remove and replace castings, subgrade correction, grade gravel for paving, pave base course, pave wear course, clean up

Hawley Avenue:
Completed:  curb & gutter, driveway aprons, ½ remove bit
To do: Finish remove remaining bituminous, remove and replace castings, remove and replace gate valve and box, grade gravel for paving, pave base course, pave wear course, turf restoration, clean up

Contractor Schedule for Week of July 31:

The Contractor plans on finishing bituminous removal on Hawley Avenue and then moving to 5th Avenue this week.  Wednesday, the valve boxes will be replaced on Hawley Avenue.  Replacing valve boxes involves shutting off the water, so residents may be affected.  Once those items are complete the Contractor will begin removing manhole castings on 5th, 15th, 16th and Hawley.  

The Contractor had taken steps to protect the roadway from the rain on Thursday, but the downpour flooded the street.  The contractor is working to make the necessary repairs.

The contractor has not yet given us a schedule for paving the wear course on Armour, Bridgepoint, Concord Exchange, or Grand Avenue.
 


All streets were approved for construction on April 3, 2017.  Park Construction has been awarded the contract for this project.  

The Contractor anticipates starting on Armour Avenue on June 19th, 2017. Work is expected to be substantially complete by late August.  Please review notice for project area map and construction information.

map can be viewed of these affected streets. 

2017-005 Mill & Overlay (M&O) Projects

2017-007 Bituminous Removal & Replacement (BRR) Projects